• CompTIA PK0-004 Dumps

CompTIA PK0-004 Dumps

CompTIA Project +

    EXAM CODE : PK0-004

    UPDATION DATE : 2023-03-30

    TOTAL QUESTIONS : 796

    UPDATES : UPTO 3 MONTHS

    GUARANTEE : 100% PASSING GUARANTEE

PDF + TEST ENGINE

$65 $84.5

TEST ENGINE Demo

$55 $71.5

PDF ONLY Demo

$45 $58.5

BEST CompTIA PK0-004 DUMPS - PASS YOUR EXAM IN FIRST ATTEMPT

PK0-004 exam has grabbed the interest of IT students with its rising need and importance in the field. In spite of being a hard core IT exam, it can easily be passed with the help of PK0-004 dumps material.This highly demanded and results-producing authentic dumps material can be obtained from Exam4help.com. When you will prepare under the guidance of veterans by using additional facilitating services, your certification is stamped with success.

As a favor to our students, we have availed free of cost demo version for quick quality check before going forward. You get here trust, find satisfaction and meet your success with expertly verified PK0-004 questions answer. You can download PDF study guide right now at very cheap and attractive price and pursue your career with fast pace. Further, it is the place where you get money back guarantee in case of, though not expected, unfortunate happening and you fail to get your desired result in your final exam. In short, you are promised for definite success with student-friendly preparatory solutions. Just join our hands and leap for your successful career.

Sample Questions

Question 1

A carpenter on a project team reports there is insufficient time to accomplish tasks on schedule. Which of the following is the FIRST step the project manager should take?

A. Assess the risk register’s new items.
B. Review the task start and finish dates.
C. Obtain additional resources.
D. Analyze the assigned hours.

ANSWER : A

Question 2

A project has fallen behind schedule for no obvious reason, so the PM has gathered the team to brainstorm. Which of the following should the PM do NEXT? 

A. Go over the meetings objectives and agenda.
B. Brief the team on which tasks have fallen behind schedule and where the project has slack.
C. Refer to the risk register to map the risks to issues and mitigation strategies.
D. Review the issue log with the project team and identify potential risks.

ANSWER : B

Question 3

A risk with minor impact has been realized. There is no change to the triple constraint. The PM should notify the:

A. internal project team.
B. key stakeholders.
C. affected team members.
D. full project team.

ANSWER : B

Question 4

A fire occurred in the production facility over the weekend, affecting the machinery being used to produce a deliverable. No injuries were reported. Which of the following is MOST appropriate for the project manager to do NEXT? 

A. Refer to the contingency plan
B. Conduct an immediate emergency team meeting
C. Perform a SWOT analysis
D. Implement the risk response plan

ANSWER : A

Question 5

A company hires a number of interns and assigns them key roles on a project. Which of the following should the project manager MOST likely anticipate?

A. Reduced quality
B. Reduced scope
C. Reduced risk
D. Reduced timeline

ANSWER : A