C_TPLM22_67 exam has grabbed the interest of IT students with its rising need and importance in the field. In spite of being a hard core IT exam, it can easily be passed with the help of C_TPLM22_67 dumps material.This highly demanded and results-producing authentic dumps material can be obtained from Exam4help.com. When you will prepare under the guidance of veterans by using additional facilitating services, your certification is stamped with success.
As a favor to our students, we have availed free of cost demo version for quick quality check before going forward. You get here trust, find satisfaction and meet your success with expertly verified C_TPLM22_67 questions answer. You can download PDF study guide right now at very cheap and attractive price and pursue your career with fast pace. Further, it is the place where you get money back guarantee in case of, though not expected, unfortunate happening and you fail to get your desired result in your final exam. In short, you are promised for definite success with student-friendly preparatory solutions. Just join our hands and leap for your successful career.
Which indicator of the event scenario specifies whether the time interval can be changed manually in
the application or not?
Please choose the correct answer.
Response:
A. Scenario
B. Preceding event
C. Reference
D. Fw
ANSWER : C
Which version serves as a proof of the project status in the past and also serves as a comparison with
the operative project?
Please choose the correct answer.
Response:
A. Milestone version
B. Operative version
C. Project version
D. Simulation version
ANSWER : C
Which of the following related to an activity stipulates the activity type and determines how an activity
is handled during calculation, scheduling and capacity planning?
Please choose the correct answer.
Response:
A. Confirmation key
B. Scheduling key
C. Control key
D. Customizing key
ANSWER : C
How can the capacity requirements of an activity be reduced?
There are 3 correct answers to this question.
Response:
A. With the period-end closing
B. By setting the status locked account assignment
C. With the final confirmation of the activity
D. With partial confirmations of the activity
E. By transferring the working times for the activity that was entered in CATS (Cross-Application Time
Sheet)
ANSWER : C,D,E
How do you evaluate and display details of orders and networks that create capacity requirements at
the work centers?
Please choose the correct answer.
Response:
A. Variable overview
B. Standard overview
C. Tabular overview
D. Capacity detail list
ANSWER : D