PMI-ACP exam has grabbed the interest of IT students with its rising need and importance in the field. In spite of being a hard core IT exam, it can easily be passed with the help of PMI-ACP dumps material.This highly demanded and results-producing authentic dumps material can be obtained from Exam4help.com. When you will prepare under the guidance of veterans by using additional facilitating services, your certification is stamped with success.
As a favor to our students, we have availed free of cost demo version for quick quality check before going forward. You get here trust, find satisfaction and meet your success with expertly verified PMI-ACP questions answer. You can download PDF study guide right now at very cheap and attractive price and pursue your career with fast pace. Further, it is the place where you get money back guarantee in case of, though not expected, unfortunate happening and you fail to get your desired result in your final exam. In short, you are promised for definite success with student-friendly preparatory solutions. Just join our hands and leap for your successful career.
An agile team and a traditional development team are working together on a project. Each
team exceeds expectations regarding deliverables; however, issues arise when the
deliverables are integrated.
What should the agile practitioner do?
ANSWER : A
A product owner complains that some of the requirements identified several Aerations ago have not been implemented. The product owner wants to know why the status of these requirements was not communicated What should the Scrum Master do?
ANSWER : B
A globally distributed project team is using email and phone calls as the only way to share
information. Delays in resolving issues often occur due to misinterpreted communications,
leading to a lower team velocity.
What steps should the project leader take to improve knowledge sharing?
A. Meet individually with each team member to identify the issues and relay information to
the remaining members through status reports.
B. Establish a live video feed between the dispersed teams to enable spontaneous engagement and collaboration on issues.
C. Request that the customer co-locate the team to overcome the communication issues,
as this is the only method to ensure agility.
D. Inform the customer of the challenges and lower velocity of the project to accomodate
for the slower delivery pace.
ANSWER : B
A projects first iteration contains item A. and its second iteration contains item B. The first iteration is behind schedule which will impact the second iteration Since items A and B are similar a team member suggests beginning the design of item B. What should the agile practitioner do?
ANSWER : B
An agile practitioner wants to ensure that stakeholders have current information about a project's progress What should the agile practitioner do?
ANSWER : D