ASM exam has grabbed the interest of IT students with its rising need and importance in the field. In spite of being a hard core IT exam, it can easily be passed with the help of ASM dumps material.This highly demanded and results-producing authentic dumps material can be obtained from Exam4help.com. When you will prepare under the guidance of veterans by using additional facilitating services, your certification is stamped with success.
As a favor to our students, we have availed free of cost demo version for quick quality check before going forward. You get here trust, find satisfaction and meet your success with expertly verified ASM questions answer. You can download PDF study guide right now at very cheap and attractive price and pursue your career with fast pace. Further, it is the place where you get money back guarantee in case of, though not expected, unfortunate happening and you fail to get your desired result in your final exam. In short, you are promised for definite success with student-friendly preparatory solutions. Just join our hands and leap for your successful career.
Your team uses Story Points to estimate User stories.
Halfway through a Sprint, you are not seeing the progress you expected. The Team feels some Stories
are not estimated correctly, when compared to other Stories.
How should you address this?
A. Complete incomplete Stories
B. Increase or re-estimate Velocity
C. Re-estimate all small Stories
D. Switch to using Ideal days
ANSWER : A
Why is a Product Owner not allowed to define the workload of the Development Team for a new Sprint?
A. This conflicts with the principle of Self-Management of the Development Team.
B. The Product Owner does not know the velocity of the Development Team.
C. The Scrum Master is responsible for the velocity of the Development Team.
D. The Scrum Master and the Product Owner must agree on the workload of the Development Team.
ANSWER : A
What is one of the most difficult challenges you face when transitioning your software development team to Scrum?
A. Introducing certain technical practices
B. Team members may already have their hands full
C. Too rapid improvements are possible
ANSWER : B
Your organization found that the Product Owner is consistently under more pressure than the developments and other participants in the project.
What is common solution for that?
A. Compiling a list with Product Owner tasks
B. Rotating the Scrum Master role
C. Using a Product Owner team
ANSWER : A
A Scrum Team suggests to have a project with 3 Sprints of 2 weeks, while the customer suggests 1
Sprint of 6 weeks.
What is the greatest advantage of having 3 Sprints of 2 weeks?
A. The customer has to invest fewer time.
B. The team can inspect and adapt 2 times.
C. The team delivers more Story Points.
ANSWER : C